Good Questions. Straight Answers.
Do I need a permit to rebuild after a fire?
Yes. Losing a home to fire does not exempt the rebuild from permitting. What the post-fire programs change is how quickly plans are reviewed — not whether a permit is required, and not whether inspections happen.
What is the difference between the City and County programs?
They are separate programs with separate rules. The City of Los Angeles program, run by LADBS, covers Palisades reconstruction and excludes geologically sensitive areas. The County program, run by Public Works, covers unincorporated communities including Altadena and requires the certifying professional to carry full code-compliance liability with enhanced insurance. Which applies depends on the jurisdiction your parcel sits in, not which fire affected it.
Does my hillside lot in the Palisades qualify for self-certification?
Possibly not. Geologically sensitive areas of the Palisades are excluded from the City program and still require geological and soils reports. On hillside parcels this should be established first, because it changes the whole schedule — and hillside site conditions frequently drive more of the outcome than the permit path does.
How long does a fire rebuild permit take now?
City plan check is reported at roughly six days, about twice as fast as before the fires. County approval timelines for standard Altadena rebuilds have been reported averaging near five months end to end. Both are meaningfully better than pre-fire norms, and both are estimates that vary with scope, site conditions and how complete the submitted set is.
Is a rebuild covered by the TDG Builder Warranty?
Ground-up new construction carries the TDG Builder Warranty under California SB 800. Remodels and conversions are not covered; workmanship on those is governed by the applicable construction contract. See the TDG Builder Warranty page for full terms.
Program details summarized from City of Los Angeles and Los Angeles County guidance current at the date above. Both programs are pilots and have already been amended once. Confirm current rules with LADBS or County Public Works before relying on any of this for a filing decision.